Monday, 8 August 2011

Works Continue Inside

 In the space of a week the work inside has moved from an empty shell, top left. To all of the inside stud wall being created, below right. 
In the space of a two and half days all of the wood work to create the stud walls were erected. And the battening of the outer-walls to take the insulated plasterboard.


 On Friday the electricians arrived en masse. In the space of one day Rob and the team from  Trent Electricals  had completed 90% of their first fix. It seemed that miles and miles of cables has been strung around the new stud work like a spiders web!
Whilst all this was going on I was starting my part of the project, The MVHR  ( Mechanical Ventilation and Heat Recovery) System. This weeks task is to install the insulated ducting . 

  The purpose of the system is control extraction of stale air and the introduction of fresh air to our home to minimise energy loss but insure fresh air is delivered through out. Air is extracted from the kitchen, wetroom, utility cupboard.  Fresh air is supplied to the bedrooms and living space. The air flow in and out is measured and balanced. The air flows are completely separated and filtered. The energy of the discharge air is transferred to the fresh and supposedly with an efficiency as high as 91%, I'll let you know how it works out.  Condensation from the discharged air is the main bi-product and is drained away. through the waste water drain. The product used is the Itho ECO4 continually runs 24 hours a day 365 days a year. 


Tuesday, 2 August 2011

New Floor and No Scaffolding














On Friday of Week 4 the newly laid pipework for the Under Floor Heating (UFH) was covered in concrete. Now up to date I thought a screeded floor was wet and sloppy cement bought to site in a big cement truck and piped in to the house. No, this was laid as a dry mix by two chaps who'd been doing it for years. A 4:1 mix with added glass fibers to add strength was tipped on a tarpaulin, on the road outside Number 1.  The mix was barrowed in to the bungalow and the guys produced a fab new floor. By the following morning the floor was rock hard. Also by the following morning the scaffolding round the bungalow came down.

.

Thursday, 28 July 2011

Roof and Floor

Week Four turns out to be another busy week. On Friday last the breatherable membrane went on to the new roof trusses. By Tuesday this week nearly all the tiles went back on, by Thursday the Velux windows were added and remaining tiles fixed in place. The roof looks perfect. By Saturday the scaffolding will be removed giving us a better view of the complete roof including  new soffit, fascias, gutters and down pipes.














The new corner steel post and lintels supporting the roof over the porch have gone in .


Whilst all of this was going on above the plumbing team were busy laying insulation and running pipes for the Underfloor Heating plus the hot and cold pipes to the taps and machines. So many Pipes! No to mention my controls in the coat cupboard! Do you think a glass door to view it would be going too far? 



Friday, 22 July 2011

Membrane On

 The end of week three and the team are pressing ahead and we fortunately have the breathable membrane on before the weekend. This will help the inside to dry out over the weekend before the underfloor insulation goes down on Monday, this is the start of the next stage the plumbers first fix. The internal scaffolding disappeared this morning as a precursor to this next stage starting. The plumbers first fix includes laying all the pipe work over the insulation from and to where its needed. This include the pipes for the underfloor heating but also all of the hot and cold services from the mains to the boiler and to the kitchen and wetroom. The pipes will then be covered in 3 inches of concrete screed.


Talking of concrete this huge wagon turned up this afternoon with all the raw ingredients to mix just the right amount of concrete for the footing of the the new retaining wall of the patio in the back garden and a new slab for the porch. Certainly stopped the traffic.

Wednesday, 20 July 2011

Week3

So where are we? Halfway through the second week and things are looking good. The weather hasn't been as good as the first weeks but the rain hasn't deterred the guys from MAS construction. With the tiles being off the roof, rain isn't perfect.    
However there is nothing inside the bungalow to spoil, there is not plaster work left on the walls or decorative woodwork. Unfortunately the roof timber will be exposed to the elements for another weekend. The roofing membrane will go on Monday and be tiled later in the week. 


Above Paul is putting the finishing touches to the roof timbers. Below, Mark puts the finishing touched to the bi-fold door opening.


 A key milestone this Friday is the completion of the new openings of doors and windows in time for the window company Stormclad to undertake detailed measurements. These will be manufactured in the coming weeks 
and installed weeks commencing 15 August.  
 Next week will be first fix for the plumbers. The underfloor heating along with the hot and cold services through out the house will be laid and covered with a cement screed.

Saturday, 16 July 2011

Steel Time

Friday of the second week was steel time! Two metal post were cut to size bolted to the concrete pads poured last week. These two upright steels support the large ridge steel that holds up the roof. A further post and beam support the trusses of the original hip roof. 



Friday, 15 July 2011

New Roof!

In the space of a week the new timbers for the bungalow roof have been fitted! And today the steels to support them will move in to place.......



Right, view of the new roof from South Ave. Below left, view from neighbors bedroom window. Below right, view from the scaffolding over front door thought to kitchen Velux. Bottom, view of openings for Velux windows over the kitchen.