However there is nothing inside the bungalow to spoil, there is not plaster work left on the walls or decorative woodwork. Unfortunately the roof timber will be exposed to the elements for another weekend. The roofing membrane will go on Monday and be tiled later in the week.
Above Paul is putting the finishing touches to the roof timbers. Below, Mark puts the finishing touched to the bi-fold door opening.
and installed weeks commencing 15 August.
Next week will be first fix for the plumbers. The underfloor heating along with the hot and cold services through out the house will be laid and covered with a cement screed.