Wednesday, 20 July 2011

Week3

So where are we? Halfway through the second week and things are looking good. The weather hasn't been as good as the first weeks but the rain hasn't deterred the guys from MAS construction. With the tiles being off the roof, rain isn't perfect.    
However there is nothing inside the bungalow to spoil, there is not plaster work left on the walls or decorative woodwork. Unfortunately the roof timber will be exposed to the elements for another weekend. The roofing membrane will go on Monday and be tiled later in the week. 


Above Paul is putting the finishing touches to the roof timbers. Below, Mark puts the finishing touched to the bi-fold door opening.


 A key milestone this Friday is the completion of the new openings of doors and windows in time for the window company Stormclad to undertake detailed measurements. These will be manufactured in the coming weeks 
and installed weeks commencing 15 August.  
 Next week will be first fix for the plumbers. The underfloor heating along with the hot and cold services through out the house will be laid and covered with a cement screed.