Well we've reached week Ten of the big renovation and the team are on target to complete the schedule on time. You'll remember that we were ahead of schedule by a week a month or so back. The main hold up was a two week delay with the installation of the bi-fold doors which finally went in yesterday. Mark and the team at MAS have been proactive finding ways to mitigate the issue but at the end of the day a number of tasks backed up behind that installation.
The boiler was fired up yesterday by Darren of Pegasus Plumbing and Heating Services Ltd. Most all of the plumbing is now complete, the final job will be connecting the kitchen sink once the granite work surface is installed later this week.