Friday, 9 September 2011
Getting Down to It
Wednesday, 7 September 2011
# It's the Final Countdown!!
Well we've reached week Ten of the big renovation and the team are on target to complete the schedule on time. You'll remember that we were ahead of schedule by a week a month or so back. The main hold up was a two week delay with the installation of the bi-fold doors which finally went in yesterday. Mark and the team at MAS have been proactive finding ways to mitigate the issue but at the end of the day a number of tasks backed up behind that installation.
The boiler was fired up yesterday by Darren of Pegasus Plumbing and Heating Services Ltd. Most all of the plumbing is now complete, the final job will be connecting the kitchen sink once the granite work surface is installed later this week.
Wednesday, 31 August 2011
Lots of Colour
by Phil Wagg
The sky is painted in amazing hues,
contrasting grey, magnificent blues.
Deep red sunsets widen many eyes,
Golden yellows of early sunrise.
Mother Nature, learned with age,
As did I, we don't do Beige.
Grasses, coloured forty shades
of green and gold on many blades.
Leafs that grow above my head
are green and brown and golden red.
Mother Nature, learned with age,
As did I, we don't do Beige.
Butterflies, there's nothing lovelier
than Red Admirals on purple buddleia.
Blackbird, Green Finch, Red Robin too,
Yellow Hammers and Tits so Blue.
Mother Nature, learned with age,
As did I, we don't do Beige.
Ann Maurice wouldn't dare
paint her walls "Coral Flair"
She would say "oh what a mistake"
to use "Blue Reflection" and "Lost Lake"
Thankfully "House Doctor" has had it's run
So Paint real colours, Have some fun.
Monday, 29 August 2011
Second Fix
The joiners also quickly fitted skirting architrave and doors. However they are not happy with the door suppliers, Howdens. Mark chased all over the Midlands for doors supposedly in stock at other depots, only to find on arrival, they were damaged.
The electricians have made a start fitting sockets, switches and down-lighters.
Thursday, 18 August 2011
Our Walls turn Pink
The platerers moved in on Thursday and have started skimming the plasterboard. Dirty job but someone has to do it! Once this is complete early next week 2nd fix will be able to start for the joiners, electricians plumbers and kitchen fitters!
Meanwhile the plasters are chasing the joiners and window fitters. Final windows need to fitted so that the reveals can be can have plaster boarding and insulating added ready for the platers.
Window Week!
Our window suppliers turned up on schedule Monday morning. The Stormclad team Ian and Keith started with the bedroom french doors and windows.
Ian and Keith removing the old inner porch door. A couple of hours later walks through our new door!
Friday, 12 August 2011
Cosy and Warm
Monday, 8 August 2011
Works Continue Inside
In the space of a week the work inside has moved from an empty shell, top left. To all of the inside stud wall being created, below right.
In the space of a two and half days all of the wood work to create the stud walls were erected. And the battening of the outer-walls to take the insulated plasterboard.
Whilst all this was going on I was starting my part of the project, The MVHR ( Mechanical Ventilation and Heat Recovery) System. This weeks task is to install the insulated ducting .
Tuesday, 2 August 2011
New Floor and No Scaffolding
On Friday of Week 4 the newly laid pipework for the Under Floor Heating (UFH) was covered in concrete. Now up to date I thought a screeded floor was wet and sloppy cement bought to site in a big cement truck and piped in to the house. No, this was laid as a dry mix by two chaps who'd been doing it for years. A 4:1 mix with added glass fibers to add strength was tipped on a tarpaulin, on the road outside Number 1. The mix was barrowed in to the bungalow and the guys produced a fab new floor. By the following morning the floor was rock hard. Also by the following morning the scaffolding round the bungalow came down.
Thursday, 28 July 2011
Roof and Floor
The new corner steel post and lintels supporting the roof over the porch have gone in .
Whilst all of this was going on above the plumbing team were busy laying insulation and running pipes for the Underfloor Heating plus the hot and cold pipes to the taps and machines. So many Pipes! No to mention my controls in the coat cupboard! Do you think a glass door to view it would be going too far?
Friday, 22 July 2011
Membrane On
Talking of concrete this huge wagon turned up this afternoon with all the raw ingredients to mix just the right amount of concrete for the footing of the the new retaining wall of the patio in the back garden and a new slab for the porch. Certainly stopped the traffic.
Subscribe to:
Posts (Atom)